Independent study
Ontario Power Generation is building the first BWRX-300 small modular reactor at Darlington, Ontario. It is the first grid-scale SMR under construction in the G7. We worked only from 41 dated public sources. Schedule Studio built the plan, and Insights forecast it and tested six decisions. The 16-page study shows what each decision buys back and the latest date to take it.
OPG's target
commercial operation of Unit 1
with no intervention, as the plan stands
With all six
Enter your email and we will send you both files.
Schedule Studio built the plan from OPG filings, regulator records and the trade press. Insights forecast it from the record of more than a million past projects. Then Insights tested each of six decisions as a separate forecast.
1
OPG's filings with the Ontario Energy Board and its quarterly reports set the plan dates. The CNSC licence and hearing record set the regulatory steps. Vendor releases fix the reactor vessel, the modules and the tunnel.
2
The plan has 1,886 work items and 2,301 links in 11 packages. It runs from the licence to construct to commercial operation, with the cooling water tunnel, the switchyard and fuel load.
3
Each milestone has an early date, a most likely date and a late date. There is a 1 in 10 chance of a date outside each side. The data date is 28 October 2026.
4
Each decision is a separate forecast in Insights. For each one, the study gives the time it buys back, the latest date to decide, and how hard it is.
283 days
can be won back with six decisions
Left as it is, the plan reaches commercial operation most likely on 12 August 2032. The range runs from 1 March 2032 to 14 March 2033, with a 1 in 10 chance outside each side. With all six decisions, the most likely date moves to 3 November 2031. That is a projection of the plan, not a prediction of what OPG will do.
127 days
won back by early commissioning readiness
Testing, fuel load and power ascension take the last two years before commercial operation. First-of-a-kind testing has the widest spread in the forecast. A ready team, tested procedures and trained operators remove much of that spread. The decision can wait until 4 June 2027.
25 Nov 2026
the first decision windows close
Secure tunnelling crews and key trades by 25 November 2026, and the forecast wins back 73 days. Bigger modules for Levels 3 to 8 must be decided by 24 November 2026. Four of the six decisions are due before 1 December 2026.
5 weeks
of spare time on the cooling water tunnel
In the plan, the cooling water tunnel has only 36 to 38 days of spare time. So the reactor building can gain only about five weeks before the tunnel sets the date. With the tunnel secured, the reactor building decisions add more. Together, the six decisions win back more than the sum of their single gains.
6 of 9
past milestones where our date was nearer than the plan
We made the first forecast from the investment decision of 8 May 2025. Then we checked it against nine milestones that OPG or the CNSC dated later. Our most likely date was nearer to the actual date than the plan in six cases, and equal in two. Five actual dates came after our late date. Two of those have only a quarter as their date. First-of-a-kind work needs a wider range, and the study says so.
We built everything on this page in a few days, working only from public information. With your own plan, the forecast and the decisions update every time you report progress. Your team sees which decisions protect the date while there is still time to take them. If you want to see it on one of your projects, talk to us.
nPlan produced this study without any involvement from, data from, or endorsement by Ontario Power Generation, GE Vernova Hitachi Nuclear Energy, AtkinsRéalis, Aecon, Kiewit, BWXT or the Canadian Nuclear Safety Commission. Every input is public. Dates and logic are nPlan's own estimates, not OPG's programme. Company and project names belong to their owners and identify only the subject of the study.