How can a data-centre owner assess risk between construction, first power and commissioning?
Megaproject Delivery
Risk
Project scheduling

How can a data-centre owner assess risk between construction, first power and commissioning?

Separate building completion, first power, integrated testing and operational readiness, then compare recovery options when the power date moves.

How can a data-centre owner assess risk between construction, first power and commissioning?
Written by
Stacey Gray
Believes the world's biggest projects deserve better than guesswork. Powered by customer stories, products that solve real problems, and the occasional gelato.

Key takeaways: For owner-side project and commissioning leads on a data-centre build whose power date has moved: treat building completion, first power, integrated systems testing and operational readiness as four milestones, each with its own owners, evidence and open assumptions. Re-forecast from first power onwards and compare recovery options against all four before accepting a revised handover date.

A data-centre contractor can report the halls close to complete while the permanent power date moves back by several weeks. The quickest response is to slide every later milestone by the same amount. Uptime Institute's Chris Brown has described what tends to follow when construction and equipment delays push a programme: "the commissioning just gets reduced in scope to meet that same schedule" (Uptime Institute Journal, May 2016).

Construction and procurement still carry substantial schedule risk, while the work needed to bring the facility into service can be hard to see in a construction progress report. When the power date moves, a fresh forecast of testing and operational readiness helps you compare recovery options before committing to a revised date.

INSIGHTS PRO · DRIVING PATHS

Forecast your current schedule and see which paths through integrated testing and handover are now most likely to drive each milestone.

Explore Insights Pro

How should an owner assess risk between construction, first power and commissioning?

Assess each milestone separately and check the dependencies between them. Building completion means the construction works are finished. First power means the permanent supply is energised. Integrated systems testing (IST) proves that power, cooling and controls work together under simulated load and failure. Operational readiness means a trained team can run the facility under approved procedures and the owner can accept it for service.

These acceptance points can overlap by hall or system. Temporary supplies or local equipment energisation can support some tests before permanent first power, where the specification and safety arrangements permit it. Define those earlier tests separately in the schedule, so a report of equipment being switched on cannot be mistaken for the permanent supply being available for integrated testing.

Building completion, permanent first power, integrated systems testing and operational readiness are separate acceptance checks for handover. Permanent first power is a prerequisite for IST, and passed IST is a prerequisite for operational readiness. Timing can overlap across halls or systems. Temporary or local power supports some equipment-level checks only where the specification and safety arrangements permit.
Each acceptance check needs its own evidence.

Why can the risk after construction be easy to miss?

Construction progress figures show little about whether the remaining systems tests and operating preparations can finish in time. One common industry framing, set out by the equipment-rental supplier Aggreko, splits commissioning of critical power and cooling plant into five levels: factory acceptance testing, site acceptance testing, pre-functional checks through initial energisation, individual system testing and, finally, integrated system testing at full load across power, cooling and IT infrastructure, including staged equipment failures and utility problems (Aggreko commissioning whitepaper, April 2020). Uptime Institute uses the same Level 5 label for integrated system testing. Numbering and content vary between owners, so check the scheme in your own specification. Test levels describe testing scope, while the four milestones describe acceptance points. The commissioning authority needs to map each test to its required supply and predecessors; an equipment test that needs energisation belongs under its temporary or permanent-power dependency, rather than being assumed a prerequisite for all building completion.

Integrated testing is where the facility is proved as a whole. Uptime Institute describes Level 5 as installing load banks that simulate IT equipment so power and cooling are fully tested, with systems operated together in every specified maintenance and failure scenario. Its reviewers also warn that cutting utility power, watching the generator start and load-banking only the generator is not commissioning (Uptime Institute Journal).

Operational readiness then depends on people as much as plant. ASHRAE Guideline 0-2019 frames commissioning as verifying that the facility meets the Owner's Project Requirements from predesign through occupancy and operation, and it includes requirements for training operations and maintenance staff (ASHRAE Guideline 0-2019 scope). Uptime's reviewers describe contractors and vendors being released before the facility's certification site visit, leaving the operations team to arrive without their project knowledge and face a stack of manuals. Keeping those specialists available for the visit is a readiness dependency to schedule.

Why is first power the dependency an owner controls least?

First power is set outside the project, by the body that connects the site, through a regulated process that is under strain. The IEA estimates that around 20% of planned data-centre projects worldwide could be at risk of delay unless grid risks are addressed, and that waits for transformers and cables have doubled in three years (IEA, Energy and AI, April 2025). These are material construction and procurement risks as well as commissioning constraints. Confirm your own connection conditions with the utility, and keep their effect on testing visible when reviewing progress.

How is the connection queue changing in Great Britain?

In Great Britain, data-centre demand has swollen the connection queue, and Ofgem is tightening the rules for keeping a place in it. Contracted demand offers rose from 41GW to 125GW between November 2024 and June 2025, at least 80GW of it from data centres (Ofgem, 29 July 2026). Ofgem has consulted on a commitment fee and progress milestones that data-centre developers would need to meet to hold their queue position, and a decision is awaited (Ofgem consultation page).

GB dates can move earlier as well as later: Ofgem says wider connections reform has brought around 7.8GW of projects forward by an average of six years. Confirm the date against your distribution network operator's offer, or against the NESO transmission offer and the relevant transmission owner's delivery conditions; ask for the connection milestones in writing (National Grid, detailed connections process).

How is large-load interconnection changing in the United States?

In the United States, federal regulators are reworking how large loads such as data centres connect to the grid, which leaves interconnection timelines in flux. On 23 October 2025 the Department of Energy directed FERC to begin rulemaking to accelerate the interconnection of large loads, including data centres (DOE, 23 October 2025).

On 18 June 2026 FERC issued show-cause orders to all six regional grid operators under its jurisdiction: PJM, MISO, SPP, CAISO, ISO-NE and NYISO. Each was directed to justify or reform its tariff rules for large loads, including co-located loads. Your serving utility gives the date, within whatever grid-operator process applies to your region, so ask it how these proceedings could affect the conditions or timing of your service.

What should the interface review show for each milestone?

For each milestone, record its prerequisites, accountable parties, evidence and open assumptions. Adapt these to your specification and contract, with a separate set per hall or phase where energisation is staged.

MilestoneWhat must be true firstAccountable
Building completionDefined construction scope complete; installation and snag status recordedMain contractor, MEP subcontractors, commissioning authority
First powerGrid works and pre-energisation checks complete; protection and utility conditions satisfiedNetwork operator or utility, owner's electrical engineer, HV contractor
Integrated systems testingSystem tests passed; permanent power, generators and load banks ready; scripts approvedCommissioning authority, contractor, vendors, operations staff as witnesses
Operational readinessIST passed; procedures approved; staff trained; spares and monitoring in placeOperator or owner's facilities team, commissioning authority

Record the evidence separately from the assumptions still awaiting confirmation.

MilestoneEvidenceAssumption to test
Building completionCompletion records, snag lists, site acceptance recordsIs "complete" defined per hall or for the whole site?
First powerUtility release, energisation record, protection and pre-energisation test recordsDoes the date cover energisation or full contracted capacity?
Integrated systems testingApproved test scripts, individual test records, load bank planHow much time is allowed for failed tests and retests?
Operational readinessTraining records, approved procedures, issue acceptance decisionsIs operations mobilisation still tied to the old power date?

Other assumptions are worth the same test: which open snags would block commissioning, whether commissioning access was assumed before completion, whether capacity arrives in stages, whether temporary power is available, how long IST takes per hall, and whether tenant or customer acceptance needs extra testing.

The assumptions column carries the most weight. A milestone can show green while resting on an assumption nobody has confirmed, and the interface review exists to turn each assumption into either evidence or a named action.

What should happen when the power date moves?

Treat the change as a new input to the forecast, then work forward through every milestone before any revised handover date is agreed.

  • Confirm what has changed. Get the revised date in writing from the network operator or utility and establish whether it covers energisation or full contracted capacity, whether capacity arrives in stages and which conditions remain open on the owner's side.
  • Agree which tests depend on permanent power. Ask the commissioning authority to mark, test by test, which need the permanent supply and switchgear in service and which could start earlier on generator or temporary supply under the specification and safety case. That split sets how much of the work after first power can move into the wait.
  • Update the dependency in the schedule logic. Link every activity that needs permanent power to the first power milestone, and link temporary-supply tests to their own enabling activities. The revised date then flows through the work that depends on it. The US Government Accountability Office calls this horizontal traceability: a schedule that accounts for the interdependence of activities and the handoffs between them (GAO Schedule Assessment Guide, GAO-16-89G).
  • Re-forecast all four milestones. Forecast building completion, first power, IST and operational readiness separately, and note which paths now drive each one. A delay to first power can turn an IST activity that had float into the driver of handover.
  • Build and compare recovery options. Develop resequencing options with the contractor, commissioning authority, vendors and operations team who would deliver them, compare each against all four milestones, and send one or two to detailed engineering, safety and acceptance review before any new handover date is agreed.

How do you compare recovery options when first power moves?

Compare them by where each one moves the risk, because two options can show the same handover date while leaving very different exposure in IST and operational readiness. Each option needs project-specific engineering and safety review.

OptionCan protectCan move risk into
Shift every later milestoneTest sequence and scopeIdle or remobilised teams
Test equipment early on temporary powerTime after first powerTemporary power interfaces, safety arrangements, possible retests
Energise hall by hall, if offeredEarlier readiness for the first hallRepeat testing as later halls join shared systems
Compress ISTThe handover date on paperTest coverage, the cut Uptime's reviewers warn about
Use the wait for readiness workOperational readiness, fewer late issuesNo handover time recovered by itself

Each option also needs sign-off from the people who carry its risk. The commissioning authority confirms any change to test timing or scope, the owner's electrical engineer confirms temporary power arrangements, the network operator or utility confirms staged capacity, and the operator confirms readiness work.

A worked example with illustrative numbers

Take a hypothetical hall where the plan needs eight weeks after first power: two weeks of equipment-level testing, four weeks of IST and two weeks of operational acceptance. The power date then moves back by five weeks. These figures are assumptions for illustration, not a project result.

  • Shift everything: handover moves from week 8 to week 13, measured from the original first power date.
  • Test equipment on temporary power during the wait: if the commissioning authority accepts those results without retest, six weeks of work remain after permanent first power, putting handover in week 11.
  • Compress IST from four weeks to two: handover also lands in week 11, with two weeks removed from integrated testing.
Illustrative week-scaled comparison: the original plan finishes in week 8. A five-week permanent-first-power slip moves unchanged work to week 13. Two weeks of equipment checks completed during the wait, with safe temporary power and results accepted without retest, leave four weeks of IST and two of acceptance, reaching week 11. Alternatively, equipment checks at weeks 5 to 7, IST at weeks 7 to 9 and acceptance at weeks 9 to 11 also reach week 11. Shorter IST leaves less test time and needs a review of proposed coverage. The early checks have no specified start week.

Both recovery options reach week 11, but their risk differs. Early equipment testing depends on safe temporary power and accepted results; shorter IST leaves less time to prove the facility works. Compare forecast durations and the proposed test coverage before sending either option to detailed engineering review.

Where does a forecast help, and where does judgement take over?

A forecast helps once the question becomes "which option holds up best across every milestone?", because that comparison needs a consistent basis. With nPlan Insights Pro, we forecast every activity using what our models have learned from more than 780,000 past project schedules. Driving Paths shows the paths most likely to affect each milestone, while Mitigation Strategies lets you test scenarios side by side. Schedule Optimisation, included in Insights Pro, helps you explore resequencing options. Any option the comparison favours still goes to your commissioning authority and engineering review.

Late-stage testing is one place such a forecast can find risk. On an 11-storey hospital extension in Boston, our forecast showed testing and balancing activities at 100% criticality, so any delay to them would directly delay the end milestone, and delays could come from leaks in ductwork, dampers or valves that only show up during testing and need rework. The recommendation was to resequence that work earlier or keep specialist resources on standby, and our published case study with the contractor Suffolk reports that Suffolk adopted it and avoided 20 days of delay, put at $1.25m in delay cost.

On a data-centre schedule, Insights Pro can forecast the current plan and each recovery option against the milestones that matter to the owner. Judgement stays with the people accountable for each milestone. Owners, planners, network operators or utilities and commissioning specialists still confirm connection availability, validate the schedule dependencies, approve test sequences and decide whether an option meets engineering, safety and acceptance requirements.

Some questions sit outside what a forecast of your schedule can answer:

  • Grid timing: we do not predict when a network operator or utility will connect your site; that sits with them and the regulatory process.
  • Missing logic: if the schedule does not yet model power and commissioning activities in enough detail, the first job is to add that logic with your planners.
  • Schedule quality: if the concern is whether the schedule is well built and maintained, schedule-health tools address that question directly, as we explain in Schedule Analytics vs nPlan.

What should an owner ask for before accepting a revised handover date?

Ask for three things at the next schedule update, before any new date is agreed:

  • both interface tables, with every open assumption either evidenced or assigned to a named person;
  • the written basis for the new power date, including whether it is energisation or full capacity and any staging;
  • a side-by-side comparison of at least two feasible recovery options against building completion, first power, IST and operational readiness, using forecast durations.

With those in hand, the decision in front of the owner becomes which option deserves detailed engineering review.

INSIGHTS PRO · MITIGATION STRATEGIES

Test each recovery option against the same forecast, milestone by milestone, before you accept a revised handover date.

Book a call with our team

Frequently asked questions

Is a finished data-centre building ready to operate?

A finished building alone does not establish readiness for service. Permanent power, integrated systems testing and operational readiness each need their own acceptance evidence and forecast. These milestones can overlap by hall or system, so the schedule must show the actual dependencies.

What is integrated systems testing in a data centre?

Integrated systems testing, often labelled Level 5 commissioning, proves that power, cooling and controls work together under simulated IT load. Uptime Institute describes it as using load banks and operating the systems together in every specified maintenance and failure scenario. Where integrated testing requires the permanent supply, a late first-power date delays those tests and their dependent acceptance work.

Which commissioning tests can run on temporary power?

The commissioning authority decides test by test under the specification and safety case. Equipment-level tests may be candidates for an earlier start on generator or temporary supply with load banks. Integrated systems testing exercises power, cooling and controls together, including the response to utility problems, which is why the interface review lists permanent power among its prerequisites.

What evidence should an owner ask for when the power date changes?

Ask for the revised date and its conditions in writing, including whether it covers energisation or full contracted capacity. Then ask for an updated schedule with every activity that needs permanent power linked to that date, and a comparison of at least two recovery options against every milestone.

Can nPlan predict when a data centre will get its grid connection?

No. The connection date is set by the network operator or utility and the regulatory process. nPlan Insights Pro forecasts the project schedule around that date, shows which paths are most likely to drive each milestone and lets teams compare recovery options once the power assumption changes.