Introducing nPlan’s Activity Correlation Explorer
AI explainability
Risk Matchmaker
Activity Correlation Explorer

Introducing nPlan’s Activity Correlation Explorer

Explainability in AI: finding risky activities off the critical path

Introducing nPlan’s Activity Correlation Explorer
Written by
Richard Bendall-Jones
Richard brings over 10 years’ experience as a Project Manager and Risk Manager on UK infrastructure projects. He is a Fellow of the Association for Project Management (APM) and the Institute of Risk Management (IRM), as well as holding an MSc in Project Management from UCL.

Updated 9.11.2026

Key takeaways

For risk managers and project controls leads, off-path risks become clearer when every activity has a forecast range. Driving Paths in Insights Pro shows which sub-critical paths could take over; the Activity Correlation Explorer described here explains how comparable past activities performed, helping the team investigate a warning before acting on it.

The critical path in a schedule update is worked out from planned durations. It marks the activities with the least float today, and it says nothing about which activities are likely to overrun, so an activity with months of float can still end up driving the completion date when work like it has a history of running long.

An off-path risk therefore needs two things before anyone acts on it: a forecast showing it can reach the end date, and an explanation of why. A warning on an activity nobody was watching is exactly the moment a team asks the AI to justify itself.

Insights Pro · Driving Paths

See the critical path and the sub-critical paths that could take it over, forecast from your own schedule.

See how Insights Pro works

Contents

  1. How can you find risky activities that are not on the current critical path?
  2. Why do AI forecasts need explaining?
  3. What does the Activity Correlation Explorer show?
  4. How does it work with Risk Matchmaker and the delay causes suggester?
  5. Why does opening the black box matter?
  6. How do UK and US guidance treat risk off the critical path?
  7. Frequently asked questions

How can you find risky activities that are not on the current critical path?

Start from a forecast for every activity and look in three places. Near-critical activities have float close to the critical path’s, judged against a threshold tailored to the project. Risk-critical paths are the ones that end up driving completion once the uncertainty in every duration is included. And some activities carry more delay-causing potential than their float suggests, wherever they sit in the logic. For each one, the team then needs to know why it was flagged before it can decide what to do.

In Insights Pro, Driving Paths visualises criticality from our forecasts, showing the critical path and any sub-critical paths that may be sources of unforeseen risk. Insights Pro also identifies the activities and themes that influence the outcome most, which is where counterintuitive risks far from the deterministic critical path come to light. The project team still validates what the forecast finds, plans the mitigation and makes the decision.

Where risk off the critical path shows up

Signal

What it tells you

Where to see it

Near-critical float

Activities that become critical after a small slip

The schedule’s float, against a project threshold

Sub-critical paths

Paths that could drive completion once durations vary

Driving Paths in Insights Pro

Delay-causing potential

Activities and themes that influence the outcome most

Insights Pro, by activity and theme

Why it is flagged

How similar past activities performed

Activity Correlation Explorer (2024 release, described below)

Why do AI forecasts need explaining?

As a tech company which uses Predictive AI for forecasting construction project activities and milestones, one of the biggest challenges we face is explaining why our AI has come up with the insights it has. When a technology provides us with an output that agrees with what we already believe, people are less inclined to need an explanation. But when these things tell us something different, we naturally (and rapidly) demand explanations. At this point, AI and specifically Deep Learning can start to appear like a black box.

And this is perfectly understandable! In my time as a project team member, I was able to see and control the inputs into what I was doing, and how it related to the outputs, so I could see why something did or didn’t make sense to me. With AI, a user receives an output, decides whether it makes sense or not, and that’s it. That can create the perception that ‘the computer is wrong’, because we’re not able to interrogate further. It can feel like a computer saying ‘just trust me’, and humanity is not ready for that just yet.

What does the Activity Correlation Explorer show?

We introduced the Activity Correlation Explorer in December 2024 to help users understand how our AI reached its conclusions. The feature descriptions below reflect that original release. Welcome, then, to the Activity Correlation Explorer (this is our internal name for the feature; we’re working on something jazzier). The Activity Correlation Explorer looks at a key activity, and then tells you what proportion of our dataset of more than 780,000 past project schedules has informed the forecast for that activity, and how these activities have historically performed:

Activity Correlation Explorer on a demo project’s key activity: 2,164 similar activities in nPlan’s dataset, 16% finished late, taking 334% longer than planned on average.

Not only does this help the user to see that their activities relate to our dataset, this also helps the user to understand why it is important, and to what extent. What I also like about it is the relationship to how people traditionally quantify discrete risk: there is a probability and an assessment of impact.

How does it work with Risk Matchmaker and the delay causes suggester?

When you combine this feature with the other features described in this post, the benefits start to multiply. Look, for example, at Risk Matchmaker, where a user can upload their risk register to see how our insights match to the risks they’ve been worrying about (or not worrying about):

Risk Matchmaker panel on the Risk Allocation tab, listing three risks from an uploaded project risk register that could affect the selected activity: equipment rental delays, quality control issues and construction delays.

Or indeed our delay causes suggester, which finds typical causes of delay for a highlighted insight:

Possible Delay Causes tab listing five suggested causes of delay for a highlighted insight: unfavourable weather conditions, improper planning, inadequate site conditions, compliance issues and labour disputes.

In my mind, all of these features start to draw the picture of what risk there might be to a project in a way that is explained, so a user can understand and explain them to others. And most importantly, to manage risk before they become issues.

Why does opening the black box matter?

Explaining the outputs of AI will continue to be a tricky issue. With these features, nPlan is opening the black box of our dataset and ML features and linking them to the world of our users, who are discussing what’s important to make decisions that matter. And by making these outputs more familiar, linked to what our users do in their day-to-day jobs, their decisions will be powered by billions of hours of project experience at the press of a button (or a few presses).

How do UK and US guidance treat risk off the critical path?

Great Britain

On NEC4 contracts, the Contractor’s programme submitted for acceptance shows float and time risk allowances (Engineering and Construction Contract, clause 31.2), and the Project Manager reviews it before accepting it. The float on an accepted programme is the deterministic picture of how far each activity can move today. An owner who wants to know which of those activities are likely to use up their float needs a forecast beside the programme, and can take what it finds into the next programme review.

United States

The GAO Schedule Assessment Guide (GAO-16-89G, December 2015) asks programme managers to monitor near-critical paths against a float threshold tailored to the programme, with the example of 5 days on a brief schedule and 2 to 3 months on a multiyear programme. It also says schedule risk analysis should not be focused solely on the deterministic critical path, because once durations are uncertain any activity may affect the completion date. GAO measures this as risk criticality: the share of simulation iterations in which an activity sits on the critical path.

Insights Pro · Mitigation Strategies

Test which mitigation on a flagged activity protects your key milestone before you commit the team to it.

Book a call

Frequently asked questions

How can I find risky activities that are not on the current critical path?

Forecast a range of durations for every activity, then check three things: near-critical activities against a float threshold set for the project, the paths that become critical once durations vary, and the activities with the most delay-causing potential. In Insights Pro, Driving Paths shows the critical path and the sub-critical paths that could take over. Then find out why each flagged activity is risky before deciding what to do.

What is a near-critical activity?

A near-critical activity has total float within a narrow range of the critical path’s float, so a small slip would make it critical. The GAO Schedule Assessment Guide says to tailor the threshold to the programme, for example 5 days on a brief schedule and 2 to 3 months on a multiyear programme.

What is the difference between the critical path and a risk-critical path?

The deterministic critical path comes from the current planned durations and logic. A risk-critical path is one that drives completion once the uncertainty in each duration is included, and it can differ from the deterministic one. GAO measures risk criticality as the share of simulation iterations in which an activity is on the critical path.

How does the Activity Correlation Explorer explain a forecast?

The Activity Correlation Explorer described in this post looks at a key activity and shows what proportion of our dataset of more than 780,000 past project schedules informed the forecast for that activity, and how those activities have historically performed.

Does Insights Pro replace the team’s risk review?

No. Insights Pro forecasts every activity and points to the activities and themes with the most delay-causing potential. The project team still validates those findings, plans the mitigation and makes the decision.

Sources

  1. US Government Accountability Office, Schedule Assessment Guide: Best Practices for Project Schedules, GAO-16-89G, December 2015 (checked 3 November 2026)
  2. GAO-16-89G full text (PDF): Best Practice 6, near-critical paths, and Best Practice 8, schedule risk analysis and risk criticality (checked 3 November 2026)
  3. GAO Schedule Assessment Guide online, The critical path method (checked 3 November 2026)
  4. GAO Schedule Assessment Guide online, Best Practice 6: Confirming that the critical path is valid (checked 3 November 2026)
  5. GAO Schedule Assessment Guide online, Best Practice 7: Ensuring reasonable total float (checked 3 November 2026)
  6. GAO Schedule Assessment Guide online, Conducting a schedule risk analysis (checked 3 November 2026)
  7. GAO Schedule Assessment Guide online, Best Practice 8: Conducting a schedule risk analysis (checked 3 November 2026)
  8. NEC Contracts FAQ: Allowance for float, Option A contract (checked 3 November 2026)
  9. NEC Contracts, NEC4 Engineering and Construction Contract (checked 3 November 2026)
  10. NEC Contracts, Why you need reasonable time risk allowances in NEC contracts, Richard Patterson and Nik Farrar, 5 December 2024 (checked 3 November 2026)